Project Details
Provide QA/ QC Crew (QA/QC Manager & QA/QC Engineers) as a third
party for supervision of the activities carried out by the contractors &
insure its compliance to specs & codes for the final acceptance & approval
of the client & consultant, the activities including but not limited to the
following:
Follow up, witness, supervise & approve : WPS, PQR, WQT implementation of
the Inspection & test plan of the project, Construction activities (Material
receiving, stringing, welding, NDT, coating, excavation, laying, backfilling,
installation of valves & equipment's, Pits installation, inspection valve &
traps rooms.
-
Project Name
Terminal Building 3 Fuel Hydrant System
(system for jet fuel providing)
-
Client
NACO-ECG / Cairo Airport Co. (CAC)
-
Location
Cairo International air port
-
Year Built
March 2006 to April 2008
-
Contractor
TAV- Holding Co. JV / EGYPT GAS
Warner Lewis JV